I update story but my burndown didn’t move why?
Burndown does not change, if Sprint end date is passed. Check Sprint end date and update it, if [...]
Burndown does not change, if Sprint end date is passed. Check Sprint end date and update it, if [...]
No, only one Sprint can be assigned to a User Story at a time.
No, only one Release can be assigned to Issue at a time.
No, only one project can be associated with a User Story.
There can be only one main Responsible of a Task. Other-users can be assigned as other Responsible.
There are 3 ways to update Item Responsible: Using Item Widget Click on a Responsible icon and search [...]
Yes, user can change items after sprint is closed.
Sprint Close does not make any changes in Sprint contents itself. It only changes status of Sprint to [...]
You cannot freeze burndown but you can print sprint burndown PDF.
Sprint Burndown chart shows the progress of items compared to UnDone items. If all items of your sprint [...]
Your Item data, having deleted status will be moved to Unmapped status Column.
You can delete statuses from the board and from status set scheme. Let’s discuss both methods. i) Via [...]
No, changes in status set, only impact the current project. Newly added Status Set scheme will be added [...]
Your all unmapped statuses will be shown under unmapped column. To remove items from unmapped column you need [...]
Your all unmapped statuses will be shown under unmapped column. To remove items from unmapped column you need [...]
Tasks associated to a User Story are not visible on the Scrumban Board. Click on task icon on [...]
All Boards are designed according to user needs. For better visibility and focus, only essential information is displayed [...]
Check if your task is dependent on any other item. Dependent task is the one, that is blocked [...]
There are multiple ways to change the status of a task or an Issue. Using Issue/Task Card Select [...]
There are 3 ways to update Task status: Using Drag and Drop on Sprint Board Select Task widget, [...]